Raid code-named “Fire” at Mochovce NPP

The NAKA raid in Mochovce concerns the supply of fire alarm systems, components, devices and work necessary for the operation of the power plant. According to the recent findings, the price was allegedly raised gradually from 3.9 million euros to almost 25 million euros.
Polícia, putá

More than year between commissioning Mochovce unit 3 and 4

The Nuclear Supervision Authority (UJD) expects the investor to specify the schedule for the completion of the Mochovce nuclear unit 4 as soon as the nuclear unit 3 is commissioned. The assembly of the machinery and cleaning processes are being performed at the nuclear unit 4 in Mochovce.
Atómová elektráreň Mochovce

V Mochovciach nezistili inšpektori žiadne nové vážne nedostatky, termín dostavby stále otázny

Úrad jadrového dozoru SR (ÚJD) nezistil počas leta žiadne vážne nedostatky pri dostavbe tretieho bloku Atómovej elektrárne Mochovce. „Žiadne nové zásadné nedostatky brániace pokračovaniu uvádzania do prevádzky neboli na stavbe zistené,“ uviedla pre portál vEnergetike.sk riaditeľka kancelárie úradu Miriam Vachová. Inšpektori ÚJD našli pri kontrolách len nedostatočné vydokladovanie splnenia požiadaviek na kvalitu. „To znamená, že držiteľ povolenia musí ešte dopracovať, doplniť respektíve sprecizovať dokumentáciu preukazujúcu kvalitu určitých zariadení a vykonaných prác,“ dodala Vachová. K potencionálnym termínom uvedenia tretieho bloku Atómovej elektrárne Mochovce do prevádzky sa ÚJD nechcel vyjadriť.
Atómové elektrárne Mochovce

Ministry wants to commission Mochovce NPP promptly

New nuclear units in Mochovce should generate profits instead of further debts. The ministry emphasised that complying with all the safety and environmental regulations in connection with the completion of Mochovce NPP project is an absolute priority.
Atómová elektráreň Mochovce SE

Mochovce chce ministerstvo spustiť čo najskôr

Na miesto dlhov už by mali nové mochovecké bloky generovať zisky. Ministerstvo však zdôraznilo, že pri dostavbe Mochoviec je ale absolútnou prioritou zachovanie všetkých bezpečnostných a enviromentálnych predpisov.
Atómová elektráreň Mochovce SE

UJD extends deadlines for Mochovce NPP

According to the Nuclear Regulatory Authority of the Slovak Republic, the need for this extension of the deadline resulted from a significant pace decline of works at the third nuclear unit between March and May 2020.
Atómové elektrárne Mochovce

Mochovce NPP will be delayed, UJD confirms

Unless the permission holder proves the fulfilment of all legislative requirements, the UJD will not issue permission for commissioning the third nuclear unit of the Mochovce NPP.
Elektráreň Mochovce

Completion of Mochovce NPP may be delayed again

The inspection of selected components is being carried out at the site of the third and fourth nuclear unit in Mochovce. Slovenske Elektrarne started inspection of components after the internal control found non-compliance with the declared material in case of two pieces of pipe.
Atómové elektrárne Mochovce